Why does everyone think BIM software alone fixes bad coordination
I keep hearing supers say they just need better Revit models, but clashing detection does nothing when the field crew never opens the model on site. On my project in Boise we had 47 unresolved clashes marked 'resolved' in the software and still hit 3 rework spots in one week. Is anyone actually checking model updates against what gets built, or are we all just trusting the upload?